25th Street Paving Improvements

Project Description

The project includes roadway improvements of 25th Street from U.S. Highway 275 to Benjamin Avenue. Approximately 80% of this project will be paid with the City's allocation of Federal Highway dollars administered by the Nebraska Department of Roads (NDOR). 

Project Status

The following is a status update as of May 4, 2012.

25th Street between Taylor Avenue and Norfolk Avenue as well as Norfolk Avenue between 26th Street and Valley View Drive will be closed to thru traffic beginning the week of May 7, 2012.  This closure will be effective for approximately 2 months for utility reconstruction, grading, paving, and traffic signal construction. 

The current closure of 25th Street between Benjamin Avenue and Maple Avenue will also remain closed to thru traffic.  This closure will be effective for approximately 5 more months during bridge replacement grading, and concrete pavement construction. 

The detour route during this phase of construction will utilize Highway 275, Taylor Avenue, 24th Street, Norfolk Avenue, Hwy 81 (13th Street), and Benjamin Avenue.  Access to local traffic along 25th Street will be maintained between the Woodwinds Apartments and the Skyview Lake Park entrance.  Pedestrian traffic will be maintained on the bike trail around Skyview Lake as well. 

If you have any questions or concerns, please contact Olsson Associates on site representative Jesse Rudolf at 308-750-8618, Project Manager Jeff Palik at 308-384-8750, or Mark Dolechek, City of Norfolk at 402-844-2020.